Lincoln Bypass

Description: Near Lincoln, Industrial Boulevard to south of Yuba County line. Construct new 4 lane expressway/freeway on new alignment.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Lincoln
Zip Code 95648, 95681
 
Senate District
04
Assembly District 04
Congressional District 04
 
Caltrans District
03
 
 
County/State Route Placer 65
Postmile Begin/End R  12.2 R  23.8
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  3961    4,795  
Lane Miles Added (HOV)      0  
Lane Miles Added (Mixed)  38.6    38.6  
Peak Period Time Savings (minutes)  268103    325,159  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Wayne Lewis (530) 741-4461   Wayne.Lewis@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Wayne Lewis (530) 741-4461   Wayne.Lewis@dot.ca.gov
Right of Way Phase
Department of Transportation Wayne Lewis (530) 741-4461   Wayne.Lewis@dot.ca.gov
Construction Phase
Department of Transportation Wayne Lewis (530) 741-4461   Wayne.Lewis@dot.ca.gov
 
Corridor System Management Plan
Department of Transportation Marlon Flournoy (530) 741-4337   Marlon.Flournoy@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $51,882 $51,882
IIP Augmentation
$0 $71,780 $71,780
CMIA
$93,715 $-24,781 $68,934
Non-bond Funding
State/Federal*
$197,701 $-123,662 $74,039
Local**
$58,483 $-9,816 $48,667
Non Budgeted ETC
$0 $0 $0
 
Total**** $349,899 $-34,597 $315,302

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$6,000 $-400 $5,600 $3,915
Design(PS&E)
$15,999 $-1,750 $14,249 $15,077
Right of Way
$73,000 $13,750 $86,750 $80,170
Construction
$254,900 $-46,197 $208,703 $206,525
 
Total* $349,899 $-34,597 $315,302 $305,686

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/01/1998 

05/01/2006 
 

 
05/01/1998 

05/01/2006 
100  05/01/1998 

05/26/2006 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2011 

10/01/2011 
 

 
01/01/2011 

10/01/2011 
100  02/01/2011 

09/30/2011 
-1 

Begin Right of Way Phase

End Right of Way Phase
02/01/2004 

10/01/2011 
 

 
02/01/2004 

10/01/2011 
02/01/2004 

10/01/2011 


Begin Construction Phase

End Construction Phase
03/01/2012 

01/01/2014 
 

 
03/01/2012 

12/15/2014 
100  05/21/2012 

10/01/2014 
-3 

Begin Closeout Phase

End Closeout Phase
01/01/2014 

01/15/2016 
 

 
12/15/2014 

12/15/2016 
100  10/30/2014 

12/30/2015 


12 
Corridor System Management Plan
Adoption Date 03/01/2009    03/01/2009  06/24/2009  -4 
Implementation Date 07/01/2010    07/01/2010  06/24/2009  12 
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 3961 4,795
Lane Miles Added (HOV) 0
Lane Miles Added (Mixed) 38.6 38.6
Peak Period Time Savings (minutes) 268103 325,159

Bond Funding Cost
Adopted:
$93,715,000
Current Approved:
$20,000,000
Actual Expenditures:
$18,519,000

 

Status as of December 31, 2023.