Lincoln Bypass |
Description: Near Lincoln, Industrial Boulevard to south of Yuba County line. Construct new 4 lane expressway/freeway on new alignment.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Placer |
City | Lincoln |
Zip Code | 95648, 95681 |
Senate District |
04 |
Assembly District | 04 |
Congressional District | 04 |
Caltrans District |
03 |
County/State Route | Placer 65 |
Postmile Begin/End | R 12.2 R 23.8 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 3961 | 4,795 |
Lane Miles Added (HOV) | 0 | |
Lane Miles Added (Mixed) | 38.6 | 38.6 |
Peak Period Time Savings (minutes) | 268103 | 325,159 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Wayne Lewis | (530) 741-4461 | Wayne.Lewis@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Wayne Lewis | (530) 741-4461 | Wayne.Lewis@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Wayne Lewis | (530) 741-4461 | Wayne.Lewis@dot.ca.gov | |
Construction Phase |
Department of Transportation | Wayne Lewis | (530) 741-4461 | Wayne.Lewis@dot.ca.gov | |
Corridor System Management Plan |
Department of Transportation | Marlon Flournoy | (530) 741-4337 | Marlon.Flournoy@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $51,882 | $51,882 | ||||
IIP Augmentation |
$0 | $71,780 | $71,780 | ||||
CMIA |
$93,715 | $-24,781 | $68,934 | ||||
Non-bond Funding | |||||||
State/Federal* |
$197,701 | $-123,662 | $74,039 | ||||
Local** |
$58,483 | $-9,816 | $48,667 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $349,899 | $-34,597 | $315,302 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$6,000 | $-400 | $5,600 | $3,915 | |||
Design(PS&E) |
$15,999 | $-1,750 | $14,249 | $15,077 | |||
Right of Way |
$73,000 | $13,750 | $86,750 | $80,170 | |||
Construction |
$254,900 | $-46,197 | $208,703 | $206,525 | |||
Total* | $349,899 | $-34,597 | $315,302 | $305,686 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
05/01/1998 05/01/2006 |
|
05/01/1998 05/01/2006 |
100 | 05/01/1998 05/26/2006 |
0 -1 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2011 10/01/2011 |
|
01/01/2011 10/01/2011 |
100 | 02/01/2011 09/30/2011 |
-1 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
02/01/2004 10/01/2011 |
|
02/01/2004 10/01/2011 |
0 | 02/01/2004 10/01/2011 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
03/01/2012 01/01/2014 |
|
03/01/2012 12/15/2014 |
100 | 05/21/2012 10/01/2014 |
-3 3 |
|
Begin Closeout Phase
End Closeout Phase |
01/01/2014 01/15/2016 |
|
12/15/2014 12/15/2016 |
100 | 10/30/2014 12/30/2015 |
2 12 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 03/01/2009 | 03/01/2009 | 0 | 06/24/2009 | -4 | ||
Implementation Date | 07/01/2010 | 07/01/2010 | 0 | 06/24/2009 | 12 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 3961 | 4,795 |
Lane Miles Added (HOV) | 0 | |
Lane Miles Added (Mixed) | 38.6 | 38.6 |
Peak Period Time Savings (minutes) | 268103 | 325,159 |
Bond Funding Cost | |
---|---|
Adopted: |
$93,715,000 |
Current Approved: |
$20,000,000 |
Actual Expenditures: |
$18,519,000 |
Status as of December 31, 2023.